Construction Planning and Management MCQ Test

  1. Time and progress chart of a construction, is also known as
  2. The technique for establishing and maintaining priorities among the various jobs of a project, is commonly known as
  3. A Milestone chart
  4. Frederick w taylor introduced a system of working known as
  5. Final technical authority of a project lies with
  6. Various activities of a project are shown on bar charts by
  7. Henry gantt developed bar charts for planning and scheduling of projects in
  8. The object of technical planning is preparation of estimates.
  9. Construction team means
  10. Site order book is used for recording
  11. What is the first stage of a construction?
  12. Which of the following option is correct?
  13. Railway projects are treated as
  14. Residential buildings are treated as
Construction Planning and Management MCQ

Take Construction Planning and Management MCQ Test to Test Your Knowledge

Practice here the best Construction Planning and Management MCQ Questions that checks your basic knowledge of Construction Planning and Management. This Construction Planning and Management MCQ Test contains 20+ Multiple Choice Questions. You have to select the right answer to the question. apart from this, you can also download here the Construction Planning and Management MCQ PDF completely free.

  • Gantt chart
  • Modified Mile stone chart
  • Critical path method chart
  • All of the above
View Answer
  • Short interval scheduling
  • Critical ratio scheduling
  • Event flow scheduling technique
  • Slotting technique for scheduling
View Answer
  • Depicts the delay of jobs, if any
  • Shows the interdependencies of various jobs
  • Shows a group of milestones in an organized way
  • Points outgoing ahead of schedule of jobs, if any
View Answer
  • Line organisation
  • Effective organisation.
  • Functional organisation
  • Line and staff organisation
View Answer
  • Chief Engineer
  • Executive Engineer
  • Assistant Engineer
  • Superintending Engineer
View Answer
  • Dots
  • Crosses
  • Vertical lines
  • Horizontal lines
View Answer
  • an owner
  • a contractor
  • an engineer
  • All of the above
View Answer
  • issue of store equipments
  • names of the casual labour
  • construction measurements
  • instructions by the executive engineers
View Answer
  • Survey of the site
  • Initiation of proposal
  • Preparation of tender
  • Preparation of estimate
View Answer
  • Earliest expected time is denoted by TE
  • Latest occurrence time is denoted by TL
  • Contractual obligation time is denoted by Ts
  • All of the above
View Answer
  • Light construction
  • Industrial construction
  • Heavy construction
  • None of the above
View Answer
  • Light construction
  • Heavy construction
  • Private construction
  • Industrial construction
View Answer
  • Rigid structure
  • Top level executions over work
  • Extraordinary delay in communications
  • All the above
View Answer
  • Updating
  • Resource levelling
  • Resource smoothening
  • Critical path scheduling
View Answer
  • an event
  • an activity
  • Both A & B
  • None of the above
View Answer